Client selections deadline tracker
Clients pick tile and fixtures late, lead times blow up, and the schedule slips on us.
For remodeler, general contractor.
In build. Each agent is set up around how your business already works, on a short call with the founder.
How it works
It reads
- selections spreadsheet
- read-only project schedule
The agent drafts
Lists open client selections against their order-by dates from supplier lead times, and drafts reminders to clients with the options still pending.
Runs weekly
You approve
Project manager approves each client reminder.
It goes to
selections status sheet and approved client reminders
It never sends, posts, pays, files or changes anything before a person at your business approves it, and never reads anything not listed above. Every step is logged, and you can pause it at any time.
What this looks like in a real week
Fictional example: Hartwell Kitchens & Baths, a nine-person remodeler in the Marina. The business, people and numbers are invented.
How it is set up today
Who is involved
- Opal Project manager
- Reza Designer
Where the information lives
- Google Sheetclient selections
- Buildertrendproject schedule
- Gmailsupplier lead times
Where it breaks
Week 1
Opal · Job site
Reminds the client to choose tile.
Week 3
Reza · Gmail
Gets a 6-week lead time from the tile supplier. Does not tell Opal.
Week 4
Client · ShowroomWhere it breaks
Picks the tile. It arrives after the install date and tile slips 3 weeks.
Why: Order-by dates are never calculated, so reminders have no deadline.
What it costs: In this example, 3 weeks of schedule lost and about $2,400 of crew reshuffling.
The same week with the agent
Monday
Agent · Selections sheet and schedule
Lists 4 open selections and their order-by dates from lead times.
Monday
Agent · Opal's inbox
Drafts a client reminder with the options still pending.
Monday
Opal · Her inboxYou approve
Approves the reminder.
Monday
Opal · Email
Sends it to the client.
Sample of what it drafts
Reminder: 2 selections due this week
Hi Erin, to keep your bathroom on schedule we need two choices by Friday, November 8. Floor tile: the supplier needs 6 weeks. Vanity faucet: 3 weeks. The three tile options Reza showed you are linked here. Reply with your picks.
The details
- How you will know it works
- schedule days lost to late selections
- Setup